to Km. 109.300 of NH 119 D Pkg-II
Original Cost
₹1494 Cr
Baseline estimate
Revised Cost
₹1546 Cr
Latest approved cost
Expenditure
₹265 Cr
Spent to date
Utilization
17.1%
Of revised cost
Cost Overrun
+3.5%
+₹52 Cr
Remaining
₹1281 Cr
Budget left
Spent
₹265 Cr
Remaining
₹1281 Cr
Total
₹1546 Cr
17.1%
Utilized
Original Cost
₹1494 Cr
Revised Cost
₹1546 Cr
Increase
+₹52 Cr
Escalation
+3.5%
Project Approved
Construction / Implementation
Original End Date
2025-07-03
Revised Completion
2027-06-30
Completed
Cost has increased by ₹52 Cr (3.5%) from the original estimate of ₹1494 Cr.
Expenditure stands at ₹265 Cr, which is 17.1% of the revised project cost.
Remaining budget: ₹1281 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.