Original Cost
₹1810 Cr
Baseline estimate
Revised Cost
₹1918 Cr
Latest approved cost
Expenditure
₹608 Cr
Spent to date
Utilization
31.7%
Of revised budget
Cost Status
+5.9%
+₹108 Cr increase
Remaining
₹1309 Cr
Budget left
Spent
₹608 Cr
Remaining
₹1309 Cr
Total
₹1918 Cr
Original Cost
₹1810 Cr
Revised Cost
₹1918 Cr
Increase
+₹108 Cr
Escalation
+5.9%
Project Approved
Construction / Implementation
Original End Date
23/11/2023
Revised Completion
31/08/2026
Completed
Cost has increased by ₹108 Cr (5.9%) from the original estimate of ₹1810 Cr.
Expenditure stands at ₹608 Cr, which is 31.7% of the revised project cost.
Remaining budget: ₹1309 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.