Original Cost
₹1426 Cr
Baseline estimate
Revised Cost
₹1426 Cr
Latest approved cost
Expenditure
₹69 Cr
Spent to date
Utilization
4.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1357 Cr
Budget left
Spent
₹69 Cr
Remaining
₹1357 Cr
Total
₹1426 Cr
Project Approved
Construction / Implementation
Original End Date
09/01/2028
Revised Completion
09/01/2028
Completed
Project is within original budget of ₹1426 Cr — no cost escalation recorded.
Expenditure stands at ₹69 Cr, which is 4.9% of the revised project cost.
Remaining budget: ₹1357 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.