Original Cost
₹908 Cr
Baseline estimate
Revised Cost
₹906 Cr
Latest approved cost
Expenditure
₹450 Cr
Spent to date
Utilization
49.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹456 Cr
Budget left
Spent
₹450 Cr
Remaining
₹456 Cr
Total
₹906 Cr
Project Approved
Construction / Implementation
Original End Date
21/07/2025
Revised Completion
31/08/2026
Completed
Project is within original budget of ₹908 Cr — no cost escalation recorded.
Expenditure stands at ₹450 Cr, which is 49.7% of the revised project cost.
Remaining budget: ₹456 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.