Original Cost
₹496 Cr
Baseline estimate
Revised Cost
₹496 Cr
Latest approved cost
Expenditure
₹165 Cr
Spent to date
Utilization
33.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹331 Cr
Budget left
Spent
₹165 Cr
Remaining
₹331 Cr
Total
₹496 Cr
Project Approved
Construction / Implementation
Original End Date
07/12/2024
Revised Completion
31/07/2026
Completed
Project is within original budget of ₹496 Cr — no cost escalation recorded.
Expenditure stands at ₹165 Cr, which is 33.4% of the revised project cost.
Remaining budget: ₹331 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.