Original Cost
₹1364 Cr
Baseline estimate
Revised Cost
₹1220 Cr
Latest approved cost
Expenditure
₹116 Cr
Spent to date
Utilization
9.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1104 Cr
Budget left
Spent
₹116 Cr
Remaining
₹1104 Cr
Total
₹1220 Cr
Project Approved
Construction / Implementation
Original End Date
03/04/2027
Revised Completion
31/12/2027
Completed
Project is within original budget of ₹1364 Cr — no cost escalation recorded.
Expenditure stands at ₹116 Cr, which is 9.5% of the revised project cost.
Remaining budget: ₹1104 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.