Original Cost
₹154 Cr
Baseline estimate
Revised Cost
₹154 Cr
Latest approved cost
Expenditure
₹70 Cr
Spent to date
Utilization
45.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹84 Cr
Budget left
Spent
₹70 Cr
Remaining
₹84 Cr
Total
₹154 Cr
Project Approved
Construction / Implementation
Original End Date
30/06/2026
Revised Completion
Completed
Project is within original budget of ₹154 Cr — no cost escalation recorded.
Expenditure stands at ₹70 Cr, which is 45.2% of the revised project cost.
Remaining budget: ₹84 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.