Original Cost
₹189 Cr
Baseline estimate
Revised Cost
₹99 Cr
Latest approved cost
Expenditure
₹26 Cr
Spent to date
Utilization
25.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹74 Cr
Budget left
Spent
₹26 Cr
Remaining
₹74 Cr
Total
₹99 Cr
Project Approved
Construction / Implementation
Original End Date
07/09/2025
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹189 Cr — no cost escalation recorded.
Expenditure stands at ₹26 Cr, which is 25.8% of the revised project cost.
Remaining budget: ₹74 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.