The Bihar Cabinet approved: Construction of 220/132/33 KV Grid Sub-station and Lines. This decision falls under Energy Department , categorized as Energy Infrastructure.

Cabinet decisions like this one shape policy and funding priorities across Bihar government departments. Other decisions from Energy Department are listed below.

Decision Summary

Major approval for a new 2x200 + 2x80 MVA grid sub-station at Mairwa and extensive transmission lines. Funding: 20% equity (₹103.41 Cr) and 80% loan (₹413.64 Cr).

Additional Details

DepartmentEnergy Department
CategoryEnergy Infrastructure
DistrictSiwan
LocationMairwa Block
Authority: Bihar Council of MinistersSource: Govt. of Bihar
?

Frequently Asked Questions

QWhat was decided in this Bihar Cabinet meeting regarding "Construction of 220/132/33 KV Grid Sub-station and Lines"?
The Bihar Cabinet approved: Construction of 220/132/33 KV Grid Sub-station and Lines. Major approval for a new 2x200 + 2x80 MVA grid sub-station at Mairwa and extensive transmission lines. Funding: 20% equity (₹103.41 Cr) and 80% loan (₹413.64 Cr). Department: Energy Department . Date: 4 February 2025.
QWhich department was responsible for this cabinet decision?
This decision was under Energy Department . Category: Energy Infrastructure. Location: Mairwa Block.
QWhat is the financial outlay for this Bihar cabinet decision?
The approved financial outlay for this decision is ₹517.05 Cr. The decision was made on 4 February 2025 by the Bihar Council of Ministers.
QWhat is the status of this cabinet decision?
Status: Approved . This cabinet decision was approved on 4 February 2025 under the Bihar government's Energy Infrastructure agenda. Track implementation and related projects on BiharInfraTales.