Cabinet Decision
Power Infrastructure Approved
Barahiya Grid Sub-station Construction
BiharInfraTales Editorial··Energy Department·Barahiya Block
Outlay
₹63.40 Cr
Status
Approved
Decided On
3 June 2025
The Bihar Cabinet approved: Barahiya Grid Sub-station Construction. This decision falls under Energy Department, categorized as Power Infrastructure.
Cabinet decisions like this one shape policy and funding priorities across Bihar government departments. Other decisions from Energy Department are listed below.
Decision Summary
Construction of a new 2x20 MVA capacity 132/33 KV Grid Sub-station and associated 132 KV LILO transmission lines.
Additional Details
DepartmentEnergy Department
CategoryPower Infrastructure
DistrictLakhisarai
LocationBarahiya Block
Authority: Bihar Council of MinistersSource: Govt. of Bihar
?
Frequently Asked Questions
- QWhat was decided in this Bihar Cabinet meeting regarding "Barahiya Grid Sub-station Construction"?
- The Bihar Cabinet approved: Barahiya Grid Sub-station Construction. Construction of a new 2x20 MVA capacity 132/33 KV Grid Sub-station and associated 132 KV LILO transmission lines. Department: Energy Department. Date: 3 June 2025.
- QWhich department was responsible for this cabinet decision?
- This decision was under Energy Department. Category: Power Infrastructure. Location: Barahiya Block.
- QWhat is the financial outlay for this Bihar cabinet decision?
- The approved financial outlay for this decision is ₹63.40 Cr. The decision was made on 3 June 2025 by the Bihar Council of Ministers.
- QWhat is the status of this cabinet decision?
- Status: Approved. This cabinet decision was approved on 3 June 2025 under the Bihar government's Power Infrastructure agenda. Track implementation and related projects on BiharInfraTales.