Bhagalpur·Bhagalpur·Bihar
Admin Approval
₹3425 L
Agreement Amount
₹3635081.82 Cr
Commencement
14 Dec 2020
Scheduled Completion
13 Jun 2023
1. Joint Inspection for lounching by Railway official at 01.12.2025 2. Launching scheme (TAD) Drawing of RUB is submitted to CBE Eastern Railway, Kolkata vide lt no.382 dated-11.05.2026 for approval. Again structural drawing has been submitted