Champaran(Motihari)·East Champaran(Motihari)·Bihar
Admin Approval
₹5278 L
Agreement Amount
₹49.91 Cr
Commencement
30 Dec 2023
Scheduled Completion
29 Jun 2026
1. P10 Pile cap work is in progress. 2. 17/20 Hammer Head Completed; remaining in progress. 3. 13/19 Deck slab. 4. Under Section 19(I) Completed. The process for determination of rate is under progress.