Champaran(Motihari)·East Champaran(Motihari)·Bihar
Admin Approval
₹7256 L
Agreement Amount
₹74.83 Cr
Commencement
30 Dec 2023
Scheduled Completion
29 Jun 2026
1. 30/33 Hammer head completed. 2. 79/134 Girder completed. 3. 14/32 Deck Slab Completed & 1 nos. deck slab reinforcement work is in progress 4. 13 span Girder Lunch 5. LA-Under Section 19(I) completed on dated 16.02.2026