Saran Works·Gopalganj·Bihar
Admin Approval
₹120 L
Agreement Amount
—
Commencement
—
Scheduled Completion
—
Bridge is located on the R.C.D road. This is sanctioned under state plan head. L.A proposal under new L.A act has been submitted vide this office letter no. 172 (We) dated 10-04-2017. Bridge work completed along with approach road. Traffic started. Rupees 13,99,017=00 transitared to DLAO Gopalganj for Land acquisition Total 25.5 Dismil land required to acquire from total 5 raiyats. A/A amount for the scheme is Rupees 120.05 Lakhs. Due to land acquisition a revised A/A for Rupees 165 Lakhs has been submitted to Department by Md, BRPNNL vide letter no.78 dated 03-02-2016 Decision for land aquisition under perpetual lease may be taken.