Construction and improvement of Bypass Road with 01 No ROB (LC-13C) from Bhutaha More (NH-107 in Km-171) to Millia Polytechnic College (SH-60) in Km 4th via Purnea-Srinagar Road from Ch.-0+000 to 9+176 (Total Length -9.176 km on Engineering, Procurement & Construction (EPC) Mode .(Pragati Yatra)
Katihar·Purnia·Bihar
Admin Approval
₹14394 L
Agreement Amount
₹78.15 Cr
Commencement
21 Feb 2026
Scheduled Completion
20 Aug 2028
Project Details
Cost & Timeline
Construction and improvement of Bypass Road with 01 No ROB (LC-13C) from Bhutaha More (NH-107 in Km-171) to Millia Polytechnic College (SH-60) in Km 4th via Purnea-Srinagar Road from Ch.-0+000 to 9+176 (Total Length -9.176 km on Engineering, Procurement & Construction (EPC) Mode .(Pragati Yatra) is a bridge construction project in Purnia district under the Bihar Rajya Pul Nirman Nigam Limited (BRPNNL), Katihar. The agreement amount is ₹78.15 Cr, and the project is currently Unknown.
BRPNNL bridges improve rural and inter-district connectivity across Bihar. Other bridge projects in Purnia district are listed below.
Remarks
Earth Work, C & G, Forest Clearing and Utility shifting work in progress. Remarks for LA: LA of New Proposed Alignment Portion is in Progress. For Remaining Portion 11(i) is completed. For Remaining Portion 19(i) is in Progress.
Frequently Asked Questions
- QWhat is the current status of "Construction and improvement of Bypass Road with 01 No ROB (LC-13C) from Bhutaha"?
- Status: Unknown. Physical achievement: N/A. On schedule. Scheduled completion: 20 Aug 2028. This is a BRPNNL bridge and road project in Purnia, Bihar.
- QWhat is the cost of this BRPNNL project?
- The agreement amount for this project is ₹78.15 Cr. Administrative approval: ₹14393.62 lakh. The project is in Katihar division, Purnia district.
- QWhich division is this BRPNNL project in?
- This project is under BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) Katihar division in Purnia district, Bihar. Scheme: Plan. AA Vide No.: 924(s).
- QWhat does BRPNNL do in Bihar?
- BRPNNL (Bihar Rajya Pul Nirman Nigam Ltd) is a Bihar government corporation responsible for bridge and road construction across rural and semi-urban Bihar. "Construction and improvement of Bypass Road with 01 No ROB (" in Purnia is one of many bridge projects tracked through the Monthly Progress Report (MPR) system monitored on BiharInfraTales.