BCD Awards Contract for Digital Museum-Cum-Conference Hall at Bihar Vidhan Sabha

Digital Museum-Cum-Conference Hall at Bihar Vidhan Sabha
Facebook
Twitter
Tumblr
WhatsApp
Reddit
LinkedIn

The construction of a Digital Museum-cum-Conference Hall at the Bihar Vidhan Sabha in Patna has officially entered the execution stage, following the awarding of the tender to contractor Arvind Kumar. The final contract stands at ₹47.20 crore, which is slightly lower than the administratively approved cost.

Approval and Timeline

The Building Construction Department granted administrative approval for the project on July 8, 2022, with a sanctioned cost of ₹48.76 crore for the financial year 2022–23. The estimated project cost was ₹48.52 crore, and the stipulated completion timeline is 18 months from the date of commencement.

Digital Museum-Cum-Conference Hall at Bihar Vidhan Sabha
Digital Museum-Cum-Conference Hall at Bihar Vidhan Sabha

Bidding and Awarding Process

The last date for bid submission was April 16, 2025. After technical and financial evaluations, the purchase order was issued on June 24, 2025.

A Tribute to Legislative Heritage

This upcoming digital museum, housed within the historic Vidhan Sabha premises, will showcase Bihar’s legislative journey and aims to become a key center for knowledge, preservation, and public engagement. The addition of a conference hall will also support legislative and academic dialogues.

Leave a Comment

Top Stories

Kusheshwar Asthan

BSTDC Receives Two Bids for Redevelopment of Kusheshwar Asthan

Bihar State Tourism Development Corporation (BSTDC) has received two bids for the redevelopment of Kusheshwar Asthan, a prominent religious site in Darbhanga. The tender for this ₹44.03 crore project was floated on February 21, 2025, through the e-tendering process. By the bid submission deadline of May 26, 2025, the following two firms submitted their bids:

Read More »
Patna Haat Project Near Gandhi Maidan

2 Bidders Technically Qualified for Patna Haat

A technical evaluation committee meeting was held under the chairmanship of the Chief Engineer of Bihar State Tourism Development Corporation Ltd. (BSTDC), Patna, to review bids received for the construction of Patna Haat near Gandhi Maidan in Patna district. The estimated cost of the project stands at ₹48.96 crore, with administrative approval for ₹47.73 crore

Read More »
AIIMS Darbhanga

HSCC Applies for Environmental Clearance for AIIMS Darbhanga Project

The proposed All India Institute of Medical Sciences (AIIMS) at Darbhanga, Bihar, is set to become a landmark healthcare and medical education hub in the state. The project is being managed by HSCC (Hospital Services Consultancy Corporation), which has formally applied for Environmental Clearance (EC) as per the statutory guidelines. With a total built-up area

Read More »
Buddhist Centre in Bodh Gaya

Tender Floated for Buddhist Meditation & Experience Centre, Bodh Gaya

The Bihar State Tourism Development Corporation (BSTDC) has floated a tender for the construction of a Buddhist Meditation and Experience Centre in Bodh Gaya, with an estimated project cost of ₹131.30 crore. The tender was officially released on June 23, 2025, and sets a completion timeline of 24 months. Tourism Infrastructure Gets a Major Boost

Read More »